More information is located HERE
April to June 15
• Prep work (water, sewer & highway) for Paving projects
April – April 30
• Water ‐ Summer Line Upgrades
April – May 15
• Sidewalk ‐ Main Street – West Side
• Sidewalk ‐ Main Street – East Side
• Sidewalk Town Pier – East Side
• Sidewalk Town Pier – West Side
• Agamont Lane Edge of Pavement Curbing
May 1 – May 15
• Water ‐ Hydrant Replacement Main St – East Side by Atlantic Ave
May 1 – May 30
• Sidewalk ‐ West Street – North Side by Bridge Street
• Paving – Otter Cliff Road
May 15 – June 15
• Water ‐ Lower Ledgelawn Avenue Service Repair
• Sidewalk ‐ Main Street – East Side by Atlantic Ave
• Sidewalk ‐ Kennebec Street / Kennebec Place (if time permits)
May 15 – June 30
• Paving – Woodbury Road
• Paving – Devon Road
• Paving – Mountain, Rockwood, east Roads
June 15 – June 30
• Paving ‐ Conners Emerson School
July 1 – November 25
• Paving ‐ County Road
• Paving ‐ Bayview Drive (Hadley Pt to Rt3 – Head of Island side)
• Paving ‐ Indian Point Road (Town Landing Road to Oak Hill Road)
Fall – TBD
• Water ‐ Hydrant Replacement at 323
Main Street
October 26 – April 30, 2024
• Water – Complete Summer
Line Upgrades
Late November ‐ TBD
• Main Street Sewer, Water
and Stormwater
Improvements Project
* Typically, the pavement plants open up in early May, sometimes late April; and usually shut down mid‐November